THANK YOU FOR ATTENDING OUR ARCHAEOLOGY OPEN DAY

THANK YOU TO EVERYONE WHO CAME ALONG TO OUR ARCHAEOLOGY OPEN DAY

Archaeology works on site are now nearing completion.

Elsewhere work is progressing well on site. Meadowbrook College's temporary school buildings are complete and are now in use by the college.

Piling preparatory works for the Swan School sports hall and the new Meadowbrook College building have been completed, with piling now under way for the sports hall.

Demolition work to the old Meadowbrook building is underway. As part of this process, all asbestos was safely removed under carefully controlled conditions.

Work on the foundations for the school's cycle store are progressing and the site offices are in place. Work on drainage and the access road are also well under way, with temporary Section 278 works to the access point now complete.